1 November 2018

Nuclear Energy Insider (UK)

EDF, Veolia target reactor dismantling gains ahead of UK closures

A joint project to develop robotics and waste technology for gas-cooled reactors will help EDF optimize UK decommissioning projects planned in the 2020s and raises Veolia’s nuclear profile.
Source : EDF, Veolia target reactor dismantling gains ahead of UK closures 19 September 2018 https://analysis.nuclearenergyinsider.com/edf-veolia-target-reactor-dismantling-gains-ahead-uk-closures

Nuclear Energy Insider, 19 September 2018

In June, France’s EDF and environmental services group Veolia agreed to co-develop robotics solutions for dismantling graphite-moderated gas-cooled reactors and a solution for vitrifying radioactive waste.

French state-controlled EDF is currently decommissioning six gas-cooled reactors in France, at its Chinon, Saint-Laurent and Bugey nuclear plant sites. The group also owns and operates 14 gas-cooled reactors in the UK which are currently set to close between 2023 and 2030.

EDF and Veolia will jointly design and deliver innovative remote solutions to access the reactor cores and cut up and extract components. In parallel, EDF and Veolia will develop a solution for the vitrification of low-and intermediate- level waste to improve the efficiency of transport and storage.

The new partnership is the latest move by EDF to expand its expertise and capture a portion of the growing nuclear decommissioning market. The global nuclear decommissioning market is worth an estimated 200 billion euros and by 2020 around 150 European reactors will have reached a 40-year lifespan.

In May, EDF’s decommissioning subsidiary Cyclife signed a partnership with Finland’s Fortum to jointly-develop services in nuclear decommissioning and waste management, focusing on the Nordic region.

In February, Cyclife secured its first nuclear waste treatment contract with Italy’s SOGIN to treat 1,800 tons of metal waste produced from three nuclear decommissioning projects. EDF and Westinghouse also won a tender to supply engineering services for the dismantling of Spain’s 508 MW Vandellos-1 gas-cooled plant.

The new robotics and waste technologies will help EDF become the world’s first company to decommission a graphite-moderated gas cooled reactor at Chinon and boost efficiency at upcoming UK decommissioning projects. Longer-term, the new learnings should improve decommissioning practices at EDF’s 58 operational pressurised water reactors (PWRs) in France.

Age distribution of EDF’s French PWR fleet

Source: World Nuclear Industry Status Report 2018 by Mycycle Schneider consulting.

For Veolia, the partnership with EDF offers a key opportunity to deploy its technology in the growing nuclear decommissioning market. The partnership builds on Veolia’s acquisition in 2016 of Kurion, a U.S.-based nuclear decommissioning services company which helped to stabilize Japan’s Fukushima Daiichi reactor following the nuclear accident in 2011. In June, Veolia entered the Canadian nuclear market after it was selected to design, fabricate, and commission a remote waste access and conditioning system in Manitoba.

Pilot project

EDF’s Chinon decommissioning project in western France represents a “pilot” project for the group’s gas-cooled reactor plans. The 200 MW Chinon A2 unit will be the first gas-cooled reactor to be decommissioned. The dismantling of non-nuclear parts and auxiliary installations in the reactor building is scheduled to be completed by 2030 and full site cleanup is scheduled to be completed by 2055, assuming the schedule is agreed by ASN, France’s nuclear safety authority.

After Chinon is decommissioned, the process will be initiated on the other five French gas-cooled reactors.

EDF chose a multi-stage approach at a pilot site in order to “optimize methods, tools, schedule and budget,” an EDF spokesperson told New Energy Update.

EDF and Veolia expect newly-developed remote control robots will perform cutting operations for reactor vessel dismantling, removing thousands of bricks which constitute the reactor core, the spokesperson said.

Robotics have already been deployed at the decommissioning of Chooz A, EDF company’s first PWR decommissioning project.

Westinghouse, the turnkey contractor for the reactor dismantling at Chooz A, is using a robot called ‘Predator’ to segment 25,000 bricks in the reactor vessel.

Scheduled for completion by 2022, the Chooz A project has helped EDF set out a tooling strategy, demonstrating the cost benefits of developing new tools versus procuring existing tools, Guilhelm Le Roy, Chief Technology Officer at Cyclife, told a conference in May.

Cyclife also plans to build an industrial-sized demonstrator near Chinon which will test and qualify decommissioning tools and different project scenarios, Roy said. Digital modelling will be used with the demonstrator to optimize decommissioning strategies for other reactors.

Other learnings from the Chinon, St Laurent, and Bugey projects have included best practice for working with alpha-contaminated waste and in asbestos conditions, Le Roy said.

“The safety authorities in France are very focused on these two issues,” he noted.

Waste transport

Nuclear operators look to minimize the duration of fuel transfer activities due to the high labor costs associated with monitoring and handling radioactive materials.

Through their partnership, EDF and Veolia will develop a solution for the vitrification of low- and intermediate- level waste using Veolia’s GeoMelt technology. This technology immobilises radioactive waste in a glass matrix, creating a stable and durable waste form which can be transferred and stored.

The partnership will expand the application of the waste vitrification technology to a wider category of nuclear waste, Tancrede Fulop, equity analyst at Morningstar, told Nuclear Energy Insider.

“Before, vitrification was considered too expensive for low and intermediate radioactive waste, and so the temporary solution was for low and intermediate waste to be put into barrels and remain on site,” Fulop said.

Veolia could gain much more from the partnership than EDF. By deploying its technology on major commercial projects, Veolia will increase its chances of winning new contracts, Fulop noted.

"Veolia will certainly use what they gain from the EDF partnership,” Fulop said.

Political pressure

EDF’s decommissioning sector growth— and its learnings from the scaling up of activities— will depend somewhat on French government policy.

EDF’s 58 French PWR reactors provide around 75% of the country’s power. In 2015, France’s previous Socialist government set a target of reducing nuclear power to 50% by 2025. Last November, President Emmanuel Macron’s centrist government postponed the target date to around 2030-2035, citing grid needs and carbon reduction restraints.

EDF will gain further decommissioning learnings when it closes its two Fessenheim PWRs in 2020 but these numbers are small when compared with Germany, for example, where 10 reactors have closed since 2011 and a further eight reactors will be closed in 2019-2022.

Source: German Federal Ministry for the environment (BMU), 2015.

The outlook for EDF’s French PWR fleet could become clearer this fall when the government unveils its long-awaited multi-year energy policy roadmap. The roadmap is expected to provide more detail on planned nuclear closures.

The sudden resignation of France’s environment minister on August 28 could signal EDF’s French nuclear plants may operate longer than previously expected. Nicolas Hulot, a long-term green campaigner and nuclear power sceptic, resigned from his post in a radio interview, citing frustration at the “small steps” being taken to tackle climate change.

His replacement, Francois de Rugy, warned September 10 that France’s nuclear generation strategy should be based on data rather than any industry allegiances.

“The important thing is to know the economic data for both nuclear and renewable energies,” he told Le Monde newspaper.

By Jax Jacobsen

More...